Symbiotic project sixth meeting

posted in: Sem categoria | 0

The sixth meeting of the Symbiotic project took place on June 6, 2017, at VTT’s premises in Helsinki, Finland. The objective of this meeting was to discuss the progress of the work, the current status of the project, and plan the next six months.

The meeting attendees included the five consortium partners, plus the supporting organisation INOVA+. During the meeting, which started at 9h15 and ended at 15h30, these organisations discussed the work done in the previous 6 months, and then the still open points, such as the details of the integration of the final device. The planning for the following semester was then decided upon.

The meeting concluded on mid-afternoon, with all the primary points needed to continue work being agreed upon.